Miami’s downtown bridge project is delayed — again. Why is it taking so long? Miami Herald - 135 days ago
Miami signature bridge delayed to 2029 with $400 million in cost overruns, lawsuits reveal The Miami Times - 136 days ago
Lawsuit blames design mistakes, defective concrete for delays in multimillion-dollar Miami roadway project NBC 6 South Florida - 136 days ago
Design errors, defective concrete blamed for delays, extra costs Miami Signature Bridge project NBC 6 South Florida